ProjectAssignmentInterval

OfficeIMO.Project

Namespace
OfficeIMO.Project
Assembly
OfficeIMO.Project
Source revision
ba882f6b0d07 with working tree changes
Modifiers
sealed

One uninterrupted allocation on a resource's effective working calendar.

Inheritance

  • object
  • ProjectAssignmentInterval

Usage

Explore 1 API references to this type

This type appears in these public API surfaces even when no hand-authored example is attached directly to the page.

Returned or exposed by 1

Properties

public DateTime Start { get; } #

Inclusive local start.

public DateTime Finish { get; } #

Exclusive local finish.

public ProjectWork Work { get; } #

Total work, including overtime. For materials, hours encode material quantity as required by MSPDI.

public ProjectWork OvertimeWork { get; } #

Overtime included in Work.

public bool IsActual { get; } #

True for recorded actual work, false for proposed remaining work.

public decimal Units { get; } #

Regular work divided by interval minutes; material intervals are consumption rates, not resource capacity.