A predecessor relationship. Lag can be working/elapsed duration or a percentage.

Inheritance

Usage

Explore 4 API references to this type

This type appears in these public API surfaces even when no hand-authored example is attached directly to the page.

Accepted by parameters 1

Properties

public ProjectTask? Predecessor { get; internal set; } #

The predecessor task, or null for an unresolved external source relationship.

public ProjectTask Successor { get; internal set; } #

The successor task.

public ProjectDependencyType? Type { get; set; } #

Dependency kind; absent source values remain absent.

public ProjectDuration? Lag { get; set; } #

Working/elapsed lag; cannot be combined with a percentage lag.

public decimal? LagPercent { get; set; } #

Percentage lag; cannot be combined with duration lag.

public bool LagPercentIsElapsed { get; set; } #

Whether percentage lag advances elapsed time instead of the successor's working calendar. Requires percentage lag.

public bool LagPercentIsEstimated { get; set; } #

Whether percentage lag carries the source's estimated marker. Requires percentage lag; calculation requires explicit normalization because application arithmetic is unqualified.

public bool? CrossProject { get; set; } #

Whether the source declares a cross-project relationship.

public string? CrossProjectName { get; set; } #

External project reference, preserved without opening it.