ProjectTaskEarnedValue

OfficeIMO.Project

Namespace
OfficeIMO.Project
Assembly
OfficeIMO.Project
Source revision
ba882f6b0d07 with working tree changes
Modifiers
sealed

Baseline budget, earned value, and actual costs for one task at an explicit status boundary.

Inheritance

  • object
  • ProjectTaskEarnedValue

Usage

Explore 1 API references to this type

This type appears in these public API surfaces even when no hand-authored example is attached directly to the page.

Returned or exposed by 1

Properties

public int TaskUid { get; } #

Task identity.

public decimal? BudgetAtCompletion { get; } #

Selected baseline cost (BAC).

public decimal? PlannedValue { get; } #

Baseline cost scheduled through StatusDate (BCWS or PV).

public decimal? EarnedValue { get; } #

Budgeted value of completed work (BCWP or EV).

public decimal? ActualCost { get; } #

Actual costs accrued through StatusDate (ACWP or AC).

public decimal? CostVariance { get; } #

Earned value minus actual costs.

public decimal? ScheduleVariance { get; } #

Earned value minus planned value.

public decimal? CostPerformanceIndex { get; } #

Earned value divided by actual cost; null when unavailable or zero.

public decimal? SchedulePerformanceIndex { get; } #

Earned value divided by planned value; null when unavailable or zero.

public decimal? EstimateAtCompletion { get; } #

BAC divided by CPI, assuming future work follows observed cost performance.

public decimal? EstimateToComplete { get; } #

Forecast remaining cost under the CPI assumption.

public decimal? VarianceAtCompletion { get; } #

Budget minus the CPI-based estimate at completion.