ProjectTaskWorkSchedule
Calculated task totals. Duration, work and physical completion remain independent measures.
Inheritance
- Object
- ProjectTaskWorkSchedule
Usage
This type appears in these public API surfaces even when no hand-authored example is attached directly to the page.
Returned or exposed by
- Property ProjectTaskSchedule.Calculation
Inherited Methods
public override Boolean Equals(Object obj) #BooleanParameters
- obj Object
Properties
public ProjectWork Work { get; } #Work-resource assignment total, excluding material quantities.
public ProjectWork ActualWork { get; } #Completed work-resource effort.
public ProjectWork RemainingWork { get; } #Remaining work-resource effort.
public ProjectDuration ActualDuration { get; } #Completed working duration, separate from effort.
public ProjectDuration RemainingDuration { get; } #Remaining working duration, excluding splits and non-working gaps.
public Int32 PercentComplete { get; } #Duration-based completion percentage.
public Int32 PercentWorkComplete { get; } #Effort-based completion percentage.
public Nullable<Int32> PhysicalPercentComplete { get; } #Caller-supplied physical completion; never inferred from dates or effort.
public Nullable<Decimal> Cost { get; } #Calculated assignment or child costs plus fixed cost, adjusted to retain entered task actual cost unless recalculation is enabled.
public Nullable<Decimal> ActualCost { get; } #Retained task actual cost, or calculated assignment or child actual costs plus accrued fixed cost.
public Nullable<Decimal> RemainingCost { get; } #Remaining calculated cost.