ProjectTaskWorkSchedule
OfficeIMO.Project
Calculated task totals. Duration, work and physical completion remain independent measures.
Inheritance
- object
- ProjectTaskWorkSchedule
Usage
Explore 1 API references to this type
This type appears in these public API surfaces even when no hand-authored example is attached directly to the page.
Returned or exposed by 1
- Property ProjectTaskSchedule.Calculation
Inherited Methods
Properties
public ProjectWork Work { get; } #Work-resource assignment total, excluding material quantities.
public ProjectWork ActualWork { get; } #Completed work-resource effort.
public ProjectWork RemainingWork { get; } #Remaining work-resource effort.
public ProjectDuration ActualDuration { get; } #Completed working duration, separate from effort.
public ProjectDuration RemainingDuration { get; } #Remaining working duration, excluding splits and non-working gaps.
public int PercentComplete { get; } #Duration-based completion percentage.
public int PercentWorkComplete { get; } #Effort-based completion percentage.
public int? PhysicalPercentComplete { get; } #Caller-supplied physical completion; never inferred from dates or effort.
public decimal? Cost { get; } #Calculated assignment or child costs plus fixed cost, adjusted to retain entered task actual cost unless recalculation is enabled.
public decimal? ActualCost { get; } #Retained task actual cost, or calculated assignment or child actual costs plus accrued fixed cost.